Step-by-step guide

  1. Go to the view Budgets
  2. Activate the step you want to control with the switch box
  3. You see the actual measurement. Set the value for a metric.
  4. You can set the value for one metric or for more.
  5. You can validate the budgets with the validate button. Once validated, the budget data are colored :
    • green if ok
    • Orange if the average of measures is near of the bugdet (Warning for budget respect)
    • Red if budget is not respected
  6. You can click on the "loupe" to see the measure on the measure view.


You need to have at least 3 iterations for the tests to activate budgets. If not the budget data are colored in gray.